Darlington Nuclear Generating Station | |
---|---|
Country | Canada |
Location | Clarington, Durham Region, Ontario |
Coordinates | 43°52′22″N 78°43′11″W / 43.87278°N 78.71972°W |
Status | Operational |
Construction began | Unit 1: April 1, 1982 Unit 2: September 1, 1981 Unit 3: September 1, 1984 Unit 4: July 1, 1985 |
Commission date | Unit 1: November 14, 1992 Unit 2: October 9, 1990 Unit 3: February 14, 1993 Unit 4: June 14, 1993 |
Construction cost | $14.4 billion CAD ($26.4 billion in 2023 dollars[1]) |
Owner | Ontario Power Generation (OPG) |
Operator | Ontario Power Generation (OPG) |
Employees | 3000+ |
Nuclear power station | |
Reactors | 4 |
Reactor type | CANDU PHWR |
Reactor supplier | AECL |
Cooling source | Lake Ontario |
Thermal capacity | 4 × 2776 MWth |
Power generation | |
Units operational | 4 × 878 MWe (NET) |
Make and model | 4 × CANDU 850 |
Nameplate capacity | 3512 MW |
Capacity factor | 63.22% (2017) 82.90% (lifetime) |
Annual net output | 23,562 GWh (2020) 764,192 GWh (lifetime) |
External links | |
Website | Darlington Nuclear |
Commons | Related media on Commons |
Darlington Nuclear Generating Station is a Canadian nuclear power station located on the north shore of Lake Ontario in Clarington, Ontario. It is a large nuclear facility comprising four CANDU nuclear reactors with a total output of 3,512 MWe when all units are online, providing about 20 percent of Ontario's electricity needs, enough to serve a city of two million people.[5] The reactor design is significantly more powerful than those used in previous CANDU sites at Pickering and Bruce, making its 4-unit plant the second-largest in Canada behind the 8-unit Bruce. It is named for the Township of Darlington, the name of the municipality in which it is located, which is now part of the amalgamated Municipality of Clarington.
The plant began construction in September 1981 and planned to start initial operations in 1985. Several delays ensued, and the construction start on Units 3 and 4 was put off until 1984 and 1985. Unit 2 entered operation in 1990, followed by Unit 1 in 1992, and Units 3 and 4 in 1993. The delays and resulting cost overruns have made Darlington a primary case study for the anti-nuclear movement in Canada, and was one of the main reasons Ontario Hydro was broken up in 1999 and its debts paid off by special billings. After initial operations and shakeout, it is often among the most reliable plants in the world in terms of capacity factor. As of 2023[update], the plant is undergoing a mid-life upgrade, with two units completed and the second two expected to complete in 2026.
Room for a second four-reactor unit had been in place since the original site selection, with a large area to the east of the current plant set aside for what was known as Darlington B. In 2006, Ontario Power Generation began the process of applying to build a two-unit plant on the B site. This project was cancelled in 2013 when the estimated cost was far beyond initial projections. In 2020 plans started to install a much smaller BWRX-300 small modular reactor on the B site, which are ongoing as of 2023[update].