Ellenbrook railway station

Ellenbrook
Station under construction but nearly finished, viewed from a public road
Ellenbrook station under construction in January 2024 viewed from The Parkway
General information
LocationThe Parkway, Ellenbrook
Western Australia
Australia
Coordinates31°46′55″S 115°57′47″E / 31.782°S 115.963°E / -31.782; 115.963
Owned byPublic Transport Authority
Operated byPublic Transport Authority
Line(s)     Ellenbrook line
Platforms1 island platform with 2 platform edges
Tracks2
Bus stands12
ConnectionsBus
Construction
Parking500 bays
Bicycle facilitiesYes
AccessibleYes
ArchitectWoods Bagot
Other information
StatusCompleted and unopened
Fare zone3
History
Opening8 December 2024 (8 December 2024)
Services
Preceding station Transperth Transperth Following station
Opening in 2024
Whiteman Park
towards Perth
Ellenbrook line Terminus
Location
Map
Location of Ellenbrook station

Ellenbrook railway station is an unopened suburban railway station in Ellenbrook, a suburb of Perth, Western Australia. The station is the north-eastern terminus of the under-construction Ellenbrook line.

Ellenbrook station consists of a ground-level island platform with a bus interchange and car park. The contract for the construction of the Ellenbrook line was awarded to Laing O'Rourke in October 2020. Construction on Ellenbrook station started in January 2022 and was completed in March 2024, making it the first new station on the Ellenbrook line to begin and complete construction. The station is planned to open alongside the rest of the Ellenbrook line on 8 December 2024.

There are planned to be five trains per hour stopping at Ellenbrook station during peak, reducing to four trains per hour outside peak. A journey to Perth station is expected to take 30 minutes. Feeder bus routes will serve the surrounding area.