Erding Ring Closure

Erding Ring Closure
Planning overview from Bavarian Transport Ministry with Erding Ring Closure, S-Bahn expansion and Walpertskirchen Link
Overview
Native nameErdinger Ringschluss
Line number5559
LocaleBavaria, Germany
Technical
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification15 kV/16.7 Hz AC overhead catenary
Route map

40.7
Freising
(446 m)
40.0
36.2
Pulling
33.5
2.2
Neufahrn-Nord
1.5
0.8
0.6
0.0
33.4
Neufahrn-Ost
33.5
Mintraching
33.8
B 11
37.4
37.9
30.1
Flughafen-West
30.8
Besucherpark
32.5
27.5
Munich Airport
24.8
23.9
Schwaigerloh
(443 m)
23.3
Wendeanlage
20.3
St2580 (Airport East Tangent)
19.8
Central Isar Canal
15.8
9.5
Walpertskirchen Link junction
8.7
15.2
8.6
14.7
8.4
Route 2082 from Moosburg
14.3
8.2
Erding-Fliegerhorst station
(460 m)
14.2
13.8
13.6
Erding
(464 m)
12.9
Sempt
12.3
Altenerding
10.0
Aufhausen
6.4
St. Koloman
5.0
Wifling
3.3
Ottenhofen
0.0
Markt Schwaben
(508 m)
7.6
Walpertskirchen Link
0.0
to Mühldorf
Source: German railway atlas[1]

The Erding ring closure (German: Erdinger Ringschluss) is a project to build a 30.2-kilometre (18.8 mi) long, double-track railway that is planned to run from Freising via Munich Airport to Erding.

  1. ^ Eisenbahnatlas Deutschland (German railway atlas). Schweers + Wall. 2009. p. 107. ISBN 978-3-89494-139-0.