Ivanpah Solar Electric Generating System | |
---|---|
Country | United States |
Location | near Ivanpah, San Bernardino County, California |
Coordinates | 35°34′N 115°28′W / 35.57°N 115.47°W |
Status | Operational |
Construction began | 27 October 2010[1] |
Commission date | 13 February 2014[2][3][1] |
Construction cost | $2.2 billion ($2.79 billion in 2023 dollars[4]) |
Owners | NRG Energy BrightSource Energy |
Employees | 60[5] |
Solar farm | |
Type | CSP |
CSP technology | Solar power tower |
Collectors | 173,500 |
Site resource | 2,717 kWh/m2/yr |
Thermal power station | |
Primary fuel | Solar energy and natural gas |
Site area | 3,500 acres (1,420 ha)[6] |
Cooling source | Air cooling |
Power purchase agreement | >$0.135 / kWh (estimated)[7] |
Power generation | |
Units operational | 3 |
Make and model | Siemens SST-900 |
Nameplate capacity | Unit 1: 126 MW Units 2 and 3: 133 MW each. Planned: 440 MW gross, Build: 392 MW gross, 377 MW net[6] |
Capacity factor | 24.1% (2018 actual) / 28.5% (Planned) |
Annual net output | 856 GW·h |
External links | |
Website | ivanpahsolar |
Commons | Related media on Commons |
The Ivanpah Solar Electric Generating System is a concentrated solar thermal plant in the Mojave Desert. It is located at the base of Clark Mountain in California, across the state line from Primm, Nevada. The plant has a gross capacity of 392 megawatts (MW).[8] It uses 173,500 heliostats, each with two mirrors focusing solar energy on boilers located on three 459 feet (140 m) tall[9] solar power towers.[8] The first unit of the system was connected to the electrical grid in September 2013 for an initial synchronisation test.[10] The facility formally opened on February 13, 2014.[2] In 2014, it was the world's largest solar thermal power station.[11][12]
The $2.2 billion facility was developed by BrightSource Energy and Bechtel.[13] The largest investor in the project was NRG Energy which contributed $300 million. Google contributed $168 million.[14] The United States government provided a $1.6 billion loan guarantee and the plant is built on public land.[15] In 2010, the project was scaled back from its original 440 MW design to avoid disturbing the habitat of the desert tortoise.[16]
Ivanpah Project Is More Than 92 Percent Complete
ECONOMIC IMPACT: Ivanpah created 1,000 construction jobs and is expected to support 61 permanent jobs.
Though Ivanpah's PPA prices are undisclosed, they are thought to be no less than the $0.135 per kilowatt-hour PPA price for SolarReserve's 110-megawatt Crescent Dunes project in Nevada, far from DOE's CSP target price of $0.06 per kilowatt-hour.
foxnews
was invoked but never defined (see the help page).