Kamuthi Solar Power Project | |
---|---|
Country | India |
Location | Kamuthi, Tamil Nadu |
Coordinates | 9°20′51″N 78°23′32″E / 9.347568°N 78.392162°E |
Status | Operational |
Construction began | February 2016 |
Commission date | March 2017 |
Construction cost | ₹4,550 crore (equivalent to ₹64 billion or US$760 million in 2023) |
Owner | Adani Green Energy |
Solar farm | |
Type | Flat-panel PV |
Site resource | appr 2100 kWh/(m2*yr) |
Site area | 2,500 acres (1,000 ha) |
Power generation | |
Nameplate capacity | 648 MWp |
Capacity factor | 24 % |
Annual net output | Appr. 1.35 TWh/yr |
External links | |
Commons | Related media on Commons |
Kamuthi Solar Power Project is a photovoltaic power station spread over an area of 2,500 acres (10 km2) in Kamuthi, Ramanathapuram district, 90 km from Madurai, in the state of Tamil Nadu, India.[1] The project was commissioned by Adani Power.[2] With a generating capacity of 648 MWp at a single location, it is the world's 12th largest solar park based on capacity.[3][4]
ABB commissioned five sub-stations to connect the solar park with the National Grid on 13 June 2016.[5][6] The Kamuthi Solar Power Project was completed on 21 September 2016 with an investment of around ₹4,550 crore (equivalent to ₹65 billion or US$780 million in 2023).[7] The solar plant consists of 2.5 million solar modules, 380,000 foundations, 27,000 metres of structures, 576 inverters, 154 transformers, and almost 6,000 km of cables.[8][9] Construction of the structures needed to mount the solar panels required 30,000 tonnes of galvanised steel.[10] Around 8,500 workers installed an average of 11 MW of capacity per day to complete the project within 8 months.[11][12]
The entire solar park is connected to a 400 kV substation of the Tamil Nadu Transmission Corp.[13] The solar panels are cleaned daily by a self-charged robotic system.[14]
Given the solar resource of around 2100 kWh/(m2*yr) an annual generation of 1.35 TWh/yr may be possible.[15] This corresponds to a capacity factor (or average power) of 24% of the peak capacity 648 MWp. Assuming a technical life time of 25 years the investment cost is 700 MUSD/(25*1.35 TWh) = 2 US cent/kWh.
{{cite web}}
: |author=
has generic name (help)