Nyhamna Gas Plant | |
---|---|
Alternative names | Nyhamna, Ormen Lange Land Facility, Ormen Lange landanlegg |
General information | |
Type | Gas terminal |
Location | Aukra, Møre og Romsdal[1] |
Coordinates | 62°49′55″N 6°55′48″E / 62.832°N 6.93°E |
Construction started | 16 April 2004 |
Completed | September 2007 |
Owner | Norske Shell |
Design and construction | |
Services engineer | Vetco Aibel, AF Group |
Civil engineer | Skanska, NCC |
Main contractor | Aker Kvaerner |
The Nyhamna Gas Plant is a large and significant natural-gas processing plant in Aukra, Møre og Romsdal, Norway. As of January 2018, Norway was the world's third-largest natural gas exporter, after Russia and Qatar.[2]