Rail Clearways Program

CityRail ticket with Rail Clearways promotional material
Berowra additional platform completed in October 2006
Hornsby additional platform completed in April 2009
Kirrawee additional platform built as part of Cronulla line duplication completed in April 2010
Lidcombe turnback platform completed in November 2010
Extra track at Riverwood laid as part of Kingsgrove to Revesby quadruplication completed in April 2013

The Rail Clearways Programme was conceived in 2004 with the aim of easing congestion of Sydney's suburban railway network, by reducing the amount of infrastructure shared by multiple services. The disparate projects at pinch points throughout the network were designed to increase passenger capacity and improve reliability. All projects were delivered by the Transport Construction Authority until it was subsumed in November 2011 by Transport for New South Wales. A new timetable was introduced in October 2013 that realised the benefit of many of the projects, and by January 2014—the programme was complete.