Telangana Super Thermal Power Project | |
---|---|
Official name | TSTPP |
Country | India |
Location | Telangana |
Coordinates | 18°45′18″N 79°28′37″E / 18.75500°N 79.47694°E |
Status | Under construction |
Construction began | 29 Jan 2016 |
Commission date | Unit 1: 3 October 2023[1] |
Construction cost | 10598.98 Crores |
Operator | NTPC |
Thermal power station | |
Primary fuel | Coal |
Power generation | |
Nameplate capacity |
|
Telangana Super Thermal Power Project(TSTPP) is in Telangana, India. The power plant is under construction with power capacity of 1600 MW (2x800 MW) in first phase and in total planned capacity of 4000 MW.[2] It is the coal based power plant of National Thermal Power Corporation. It is being built near Ramagundam city in Peddapalli District.[3] The first Unit, 800MW, was inaugurated by PM Modi on 3 October 2023.[4][5] The second unit was inaugurated by PM Modi on 4 March 2024.[6]